How Much Concrete for a Patio?

Answer first: concrete volume in cubic yards = length (ft) × width (ft) × thickness (in) ÷ 12 ÷ 27, plus 5–10% waste, rounded up to the nearest half yard. A 10 × 10 ft patio at 4 inches thick needs 1.23 cubic yards — order 1.5. A 15 × 20 ft patio at 4 inches needs 3.70 yards — order 4.5.

The formula in four steps

  1. Measure in consistent units. Length and width in feet, thickness in inches — but convert thickness to feet (divide by 12) before multiplying. Mixing feet and inches without converting is the most common estimating error, and it puts the result out by a factor of twelve.
  2. Apply the volume formula. Volume in cubic feet = length × width × thickness ÷ 12. Divide by 27 for cubic yards, because one cubic yard is 27 cubic feet. A useful sanity check: one cubic yard covers 81 square feet at 4 inches thick.
  3. Add a waste factor. Real slabs consume more concrete than geometry predicts — forms deflect outward, the subgrade is never perfectly flat, and some material always stays in the chute, pump and wheelbarrow. Use 5% for a simple rectangle on a firm base, 10% for a typical residential slab, and 10–15% for irregular shapes or rough ground.
  4. Round up to the ordering increment. Ready-mix plants batch in half-yard steps, so after adding waste, round up. If the result is under 3–4 yards, expect a short-load fee — at small volumes, compare against bagged concrete (see ready-mix vs bags).

Worked example: 15 × 20 ft patio, 4 in thick

  1. Thickness: 4 ÷ 12 = 0.333 ft.
  2. Volume: 15 × 20 × 0.333 = 100 cu ft.
  3. Cubic yards: 100 ÷ 27 = 3.70 yd³.
  4. Waste (10%): 3.70 × 1.10 = 4.07 yd³.
  5. Order: 4.5 cubic yards.

Common patio sizes

All figures at 4 inches thick, with 10% waste included in the order column. Bag counts are 80 lb bags.

Patio sizeAreaVolumeOrder (ready-mix)80 lb bags
8 × 8 ft64 sq ft0.79 yd³1 yd³40
10 × 10 ft100 sq ft1.23 yd³1.5 yd³62
10 × 12 ft120 sq ft1.48 yd³2 yd³74
12 × 12 ft144 sq ft1.78 yd³2 yd³88
12 × 20 ft240 sq ft2.96 yd³3.5 yd³147
15 × 20 ft300 sq ft3.70 yd³4.5 yd³184
20 × 20 ft400 sq ft4.94 yd³5.5 yd³245

Run your exact size through the concrete calculator — it gives the volume, the bag count and, if you enter prices, the cost both ways.

Thickness: 4 inches is the default

Four inches is standard for patios, sidewalks and shed slabs. It sits above the residential code minimum of 3½ inches and carries foot traffic, furniture and a grill without help. Going to 6 inches adds 50% to the order — a 10 × 10 patio goes from 1.23 to 1.85 cubic yards — and on an unreinforced slab it buys almost nothing in strength. See how thick a concrete slab should be for the full reasoning, including the base and joints that matter more than the extra inch.

Irregular shapes and thickened edges

L-shapes: split into two rectangles, calculate each, and add. Circles: volume = π × radius² × thickness — a 10 ft round patio at 4 inches is 26.2 cu ft, about 0.97 yd³. Slopes and thickened edges: many slabs go from 4 inches in the field to 8–12 inches at the perimeter; treat the thickened band as its own rectangle at the deeper dimension. When a slab varies continuously in thickness, use the average depth, measured at several points rather than just the ends.

Before the truck arrives, stake and string your forms, then re-measure the actual formed dimensions and re-run the calculation. Forms rarely land exactly on plan, and two minutes of checking beats guessing when the driver asks how much.

Why running short costs more than over-ordering

Under-ordering is the most expensive small mistake in DIY concrete. Ready-mix sets in about 90 minutes; if the truck runs out before the forms are full, the pour stops, a cold joint forms where new concrete later meets old, and you pay a second delivery fee for the balance. Over-ordering wastes money at roughly $150–$200 per cubic yard (typical prices vary by area) — but a short pour costs the second fee plus a visible seam that weakens the slab. The 10% waste allowance is the cheapest insurance on the job.

Frequently asked questions

How much concrete do I need for a 10x10 slab?

At 4 inches thick, a 10×10 slab needs 1.23 cubic yards. Add 10% waste and round up: order 1.5 cubic yards of ready-mix, or about 62 bags of 80 lb mix.

How much does a yard of concrete cover?

One cubic yard covers 81 square feet at 4 inches thick, 65 square feet at 5 inches, and 54 square feet at 6 inches.

Is it cheaper to order slightly more concrete?

Yes. Leftover concrete costs a few dollars per cubic foot; running short mid-pour creates a cold joint, a second delivery fee, and often a visible seam that weakens the slab.