Ready-Mix vs Bags: Which Is Cheaper?

Answer first: bags are cheaper only for small jobs. Under about one cubic yard, buying bags wins. Over about two cubic yards, a delivered ready-mix truck is cheaper on both the concrete and your back. The one-to-two-yard range in between is genuinely close and worth pricing both ways.

What each option costs by volume

Bagged concrete is counted in 80 lb bags, each yielding 0.60 cubic feet, so a cubic yard takes 45 of them. Ready-mix is sold by the cubic yard, delivered. Typical prices vary by area, but using commonly quoted figures — about $6.25 for an 80 lb bag and about $160 a yard for delivered ready-mix — the comparison looks like this (material only, no waste added):

Volume80 lb bagsBag costReady-mix delivered
0.5 yd³23$144$80 plus fees
1 yd³45$281$160 plus fees
2 yd³90$563$320 plus fees
3 yd³135$844$480 plus fees
5 yd³225$1,406$800

On the concrete alone, the truck wins at every size from half a yard up: a yard of bags is $281 of material against $160 for the same yard delivered. You are paying for the bag, the packaging and the convenience of buying it off a shelf, and none of that scales in your favour.

What the truck adds — and when bags still win

Two costs sit on top of the per-yard price and hit small orders hardest:

Put the fee back in and the small sizes tighten up. A half-yard delivered is about $80 of concrete plus $100 to $300 in fees — $180 to $380 against $144 of bags. A single yard is $160 plus the fee, $260 to $460 against $281 of bags, which straddles the bag price and is why that band is genuinely close. By two yards the truck is $320 plus the fee against $563 of bags, so it is usually ahead; past two yards it pulls away for good.

Work out your volume first with the concrete calculator — it gives both the bag count and, if you enter prices, the cost each way.

Price is not the only factor

Three things outweigh a small price difference, and all three favour ready-mix:

One factor favours bags, and it is decisive when it applies: access. If a truck cannot get within chute reach of the pour — a back garden, a tight side passage — bags are the only option, and the extra cost is simply the price of the site.

How to decide in ten seconds

  1. Work out the volume with the calculator.
  2. Under one cubic yard? Bags, unless access is easy and you want the speed.
  3. Over two cubic yards? Ready-mix. The labour alone settles it.
  4. Between one and two yards? Genuinely close. Price it both ways, then ask whether you would rather spend the difference or a day of your life mixing.

Whichever route you choose, buy 5 to 10 percent more than the calculated volume. The most expensive concrete is the batch you did not order and now have to add on top of a half-set slab. For the bag counts at any size, see how many bags for a 4x4 slab; for a bigger project, see how much concrete for a patio.

Frequently asked questions

Is it cheaper to buy bags or get a concrete truck?

Only for small jobs. Under about a cubic yard, bags win because the truck’s delivery and short-load fees outweigh its cheaper concrete, and many suppliers will not deliver so little. Above about two cubic yards a delivered truck is cheaper on both the material and the labour.

How many 80 lb bags equal a truck load?

45 bags of 80 lb mix make one cubic yard, since each yields 0.60 cubic feet. A 3-yard delivery is 135 bags; a 5-yard load is 225.

At what size should I switch from bags to ready-mix?

Around one to two yards. The crossover is set by the flat short-load fee and the hours of mixing, not by the price per yard, where the truck is cheaper at every size from half a yard up.